9 Replies Latest reply on Jan 21, 2020 4:48 PM by Tully Krastins

    Control-M Calendar for 6th Business Day

    Tully Krastins
      Share This:

      Perhaps I'm brain dead due to the year flying by me so quickly but suddenly I can't figure out calendaring any more.

       

      My requirement is to schedule an application to run Monday - Saturday starting on the 6th business day of the month. I am using RBCs in a SMART folder. I have a WORKDAYS calendar which is Mon-Fri minus US Holidays. I can add a Saturdays RBC but only holidays in the 1st week are non-processing days. I don't want to have to create any regular calendars that need to be updated annually.

       

      I'm afraid I need someone clever to do the thinking for me (again, or is it still?)

       

      TIA

      Tully