12 Replies Latest reply on Nov 15, 2019 3:10 AM by Bhanu Prakash Badiginchala

    Job with quantitative resource gets stuck in waiting mode

    Helmut Hehenberger
      Share This:

      Hi all,

       

      I've created quantitative resources to run max 5 jobs parallel. When the condition to run is filled the first 5 jobs are starting and the rest stuck in wait status. For each job I set Required Quantity to 1.So if one job is finished the resource should be free for the next one thougth.

       

      I've found already a doc about it but it was for v6. and we run 9.0.18 https://communities.bmc.com/docs/DOC-66845

       

      Some ideas why my jobs are not running?

       

      Regards