    order as independent flow not working

    Michael Steffen

      We are running Control-M Version 9.0.00.000 Fix Pack 9.0.00.500. On occasion, we need to order in an additional run of an application that is already in the current days schedule. We would select "order as independent flow" on the order window so that a unique suffix would be added to the IN/OUT Conditions in the jobs for this additional run to avoid impacting our normal schedule. However, lately, when we do this there is no unique suffix added to the conditions. Not sure exactly when this started happening. Possibly after our last upgrade but I know that this feature used to work. Is anyone else having this problem or have any idea why we may be experiencing this issue? This is a real problem for us as our IN/OUT Conditions can get quite involved.